Chengdu, Sichuan Province Strengthens Military Facilities Protection by Leveraging Government Services Platform
Chengdu, Sichuan Province Strengthens Military Facilities Protection by Leveraging Government Services Platform — Online Project Submission, Joint Military-Civilian Review
■ Wang Leilei, Yang Shiqiao
[Diagram: Operational diagram of Chengdu, Sichuan Province's Military Facilities Protection Consultation and Review System]
"In the past, submitting a construction project application sometimes meant making many trips just to get a single stamp. Now information travels online — it saves both worry and effort." Recently, the head of a land-use entity in Wuhou District, Chengdu, Sichuan Province, was in high spirits after a project was smoothly approved. Like that entity, when planning construction projects that may affect military facilities, multiple units in Chengdu need only submit project applications online, without having to coordinate face-to-face with approving authorities, and can receive feedback within a short period of time.
It is reported that since early 2025, the city has used its Military Facilities Protection Consultation and Review System to complete reviews of more than 1,500 construction projects that may affect military facilities, with an average processing time of 2.7 working days per project — a substantial improvement in approval efficiency.
"Two years ago, things looked nothing like this." The head of the National Defense Mobilization Office (国防动员办公室) of Chengdu's Xinjin District noted that previously, when planning construction projects that might affect military facilities, land-use entities had to coordinate on their own with garrison troops, military organs, and other units. The project submission and approval process was irregular and inefficient, consuming considerable effort.
"By leveraging the government services platform, military facilities protection work has been brought onto a standardized track (规范化轨道)." The city's National Defense Mobilization Office (国动办) and the Garrison Command's Mobilization Department reached a consensus through research: seizing the opportunity presented by the upgrade of the city's engineering project review platform, they would establish a Military Facilities Protection Consultation and Review System covering both the city and district levels. Within the framework of that platform, the goal was to achieve online project submission, preliminary review by relevant departments, submission of specific opinions by military facilities management units, and unified feedback of opinions by the system. In the course of national defense mobilization adjustment and reform (国防动员调整改革), the city's National Defense Mobilization Office and the Garrison Command's Mobilization Department formed a joint office under the city's National Defense Mobilization Committee (国动委), jointly assuming responsibilities for national defense mobilization planning and construction, comprehensive coordination, and related duties. This change created favorable conditions for leveraging the government services platform to standardize military facilities protection work.
"While submitting the project application to the District Planning and Natural Resources Bureau, you send the project application form over the internet to the National Defense Mobilization Office project approval desk at the District Government Services Center — no need to make a separate trip." The head of a land-use entity in Chengdu's Jinniu District remarked with deep feeling that submitting project applications, which a few years ago required running around to multiple offline offices, has now become a single online submission — far more convenient and efficient.
After the National Defense Mobilization Office project approval desk personnel at the district level conduct a reasonableness review of the project application, they forward it via a dedicated account to the Military Affairs Section (军事科) of the District People's Armed Forces Department (人武部). The District National Defense Mobilization Office and the District People's Armed Forces Department Military Affairs Section serve as the director unit and deputy director unit, respectively, of the District National Defense Mobilization Committee Joint Office; regular joint meetings and joint handling of situations by personnel from both units have become standard practice.
Personnel from the District People's Armed Forces Department Military Affairs Section display information about the construction project — including longitude and latitude coordinates and building dimensions (length, width, and height) — on a map, and through comparison determine whether the project falls within the scope of military facilities protection. If there are objections, the relevant information is compiled, printed, and delivered in person to the military facilities management unit to solicit its opinion.
The military facilities management unit, in accordance with legal provisions, organizes personnel to conduct an assessment, determining whether the project upon completion would affect the safety and operational effectiveness (使用效能) of military facilities, and provides timely feedback to the District People's Armed Forces Department Military Affairs Section based on the assessment results. Based on the feedback from the District People's Armed Forces Department Military Affairs Section, the District National Defense Mobilization Office informs the land-use entity of the review result for the project; if approval is not granted, careful explanatory work is carried out.
The operation of the Military Facilities Protection Consultation and Review System depends on close cooperation between the city- and district-level National Defense Mobilization Offices and the two levels of military organs. The former are primarily responsible for interfacing with government departments and project-submitting entities, completing tasks such as application acceptance, registration and confirmation, and delivery of opinions; the latter are primarily responsible for interfacing with local military facilities management units, completing tasks such as project verification, written consultation for opinions, and feedback of opinions — achieving both clear delineation of responsibilities and close coordination with seamless integration (无缝衔接).
The review of projects submitted by land-use entities is conducted in accordance with laws and regulations including the Law on the Protection of Military Facilities (军事设施保护法). The Chengdu National Defense Mobilization Committee Joint Office guides military and civilian staff to accurately grasp the content of legal provisions and to insist on lawful review and conduct in accordance with regulations (依法审查、按章办事), through organizing thematic study sessions, using meetings as training opportunities, and conducting targeted education.
"The local government services platform has provided favorable operating conditions for the review system, and has also set high standards for our work." A relevant official from the Chengdu National Defense Mobilization Office stated that in the next phase, they will conduct in-depth analysis of typical cases arising from their work, promote successful experience and practices, and address shortcomings, so that the Military Facilities Protection Consultation and Review System operates more smoothly and efficiently, and so as to further mobilize the enthusiasm and initiative (积极性主动性) of the general public in protecting military facilities.
---
**Background Information**
**Relevant Provisions of the Law on the Protection of Military Facilities**
When local people's governments at or above the county level formulate national economic and social development plans or arrange construction projects that may affect military facilities protection, and when relevant departments of the State Council and local people's governments formulate territorial spatial plans (国土空间规划) and other plans, they shall give consideration to the needs of military facilities protection and shall solicit written opinions from the relevant military organs in accordance with regulations. Where necessary, the local people's government may, together with relevant departments and relevant military organs, conduct an assessment of the construction project.
When relevant departments of the State Council or relevant departments of local people's governments at or above the county level approve the construction projects specified in the preceding paragraph, they shall review whether opinions have been solicited from military organs in accordance with regulations; where opinions have not been solicited from military organs as required, they shall require that opinions be supplementarily solicited; where changes to the content of a construction project occurring during the approval process may affect military facilities protection, opinions from the relevant military organs shall be solicited again.
The relevant military organs shall provide written reply opinions within thirty days of receiving the written consultation; where it is necessary to request instructions from a higher military organ or where survey, measurement, or testing is required, the reply period may be appropriately extended, but shall generally not exceed ninety days.
Diagram by: Hu Shuo